Holy Family School Phase 1 Construction Project Schedule

Now that the Ceremonial Groundbreaking has been held for the new Holy Family School Phase 1 Project, the schedule for the project is a point of curiosity. A tentative project schedule follows. This schedule can be positively or negatively affected by things like weather, supply chain issues, etc. but this is the targer schedule

4/21/2023 - Ceremonial Groundbreaking - COMPLETED

5/05/2023 - 98% design drawing completion - COMPLETED

5/31/2023 - Final Design Development from Chapman Sisson Architects

6/15/2023 - Final pricing from General Contractor Fite Building Company

6/15/2023 - Variances granted by Huntsville Planning Commission

6/20/2023 - Final City and State Approvals

7/15/2023 - Final Approval and Contract signing by Bishop Raica

8/15/2023 - Begin Construction

Dec 2024 - Construction completion and occupancy 

Questions or comments may be directed to John Filippo at jvfilippo@icloud.com.